As many as 412 infra projects show cost overruns of Rs 4.77 trn in August

According to the report, the expenditure incurred on these projects till August 2023, is Rs 15,57,188.10 crore, which is 52.28 per cent of the anticipated cost of the projects

Work on the Purvanchal Expressway in progress. Infra projects, which the previous regime proposed and started, are incomplete for lack of funds,  sloppy pace of work, or allegations of corruption.	Photo: UPEIDA

Representative image | Photo: UPEIDA

Press Trust of India New Delhi

Listen to This Article

As many as 412 infrastructure projects, each entailing an investment of Rs 150 crore or more, have been hit by cost overruns of more than Rs 4.77 trillion in August this year, an official report said.
According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects worth Rs 150 crore and above, out of 1,762 projects, 412 reported cost overruns and as many as 830 projects were delayed.
"The total original cost of implementation of the 1,762 projects was Rs 25,01,400.62 crore and their anticipated completion cost is likely to be Rs 29,78,681.31 crore, which reflects overall cost overruns of Rs 4,77,280.69 crore (19.08 per cent of original cost)," the ministry's latest report for August 2023 said.
According to the report, the expenditure incurred on these projects till August 2023, is Rs 15,57,188.10 crore, which is 52.28 per cent of the anticipated cost of the projects.
However, it stated that the number of delayed projects decreased to 624, if delay is calculated on the basis of the latest schedule of completion.
Further, it stated that for 339 projects, neither the year of commissioning nor the tentative gestation period has been reported.
Out of the 830 delayed projects, 194 have overall delays in the range of 1-12 months, 190 have been delayed for 13-24 months, 323 projects for 25-60 months and 123 projects have been delayed for more than 60 months.
The average time overrun in these 830 delayed projects is 36.96 months.
Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.
Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems were among the other reasons.
The report also cited state-wise lockdowns due to Covid-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.
It has also been observed that project executing agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.

Also Read

408 infra projects show cost overruns of Rs 4.80 trillion in May: Report

346 infra projects show cost overruns of Rs 4.46 trillion, says report

As many as 388 infra projects show cost overruns of Rs 4.65 trn in July

As many as 393 infra projects show cost overruns of Rs 4.64 trn in June

354 infra projects show cost overruns of Rs 4.55 trn, 821 projects delayed

Assam govt approves Rs 5,197 cr project for power sector modernisation

Madhya Pradesh auctions 22 mineral blocks, to earn Rs 38,100 crore

Can't interfere in dispute between Akasa Air and its pilots: DGCA

Sidbi inks agreement with DLAI, aims to boost India's fintech sector

Trai recommends measures to boost telecom infra in north-eastern states

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

First Published: Sep 24 2023 | 11:38 AM IST

Explore News